Another silly question regarding the transmissability of power.
I am back with another silly doubt of mine!:hehehe:
Suppose I have a power plant of my own. I can produce 20MW of power. But the substation near my plant has users who only consume a total of 3MW of power. Before I start up my plant, I studied the sub-station.Its a 33/11kV substation. I saw that it is initially consuming power from another substation with is a 132/33kV substation. A thought struck my mind. If I do supply the 33/11kV substation with all my power, can I be able to connect and transfer my power to the 132/33kV substation? That is, if I give 20MW to the 33/11kV substation, will it export the excess power back to the 132/33kV grid? I can't connect the power plant directly to the 132/33kV substation as it is 40km away. Laying down 40km of transmission line will make my investors really unhappy.
I require the answer for this question really fast. Please let me know about it. Thank you.
Again, sorry for taking time.