    you mean estimate of materials?
    if yes then it depends on the mortar thickness and unit size. You can calculate the estimate per meter cube by simple mathematics.

  • Mahendra Kumar Kain

    @mahendra-kumar-xpF2Mi • Jan 26, 2013

    AnilkumarMishraWhat is the consumption formula for materials in brickwork and plastering ?
  • Mahendra Kumar Kain

    @mahendra-kumar-xpF2Mi • Jan 26, 2013

    Quantities of ingredients for any item of civil engg. be it brickwork,concrete work,woodwork etc.( for 1 unit of measurement) can be known from CPWD Analysis of Rate Books.