How much Time it take for the same Work ?

rengaraj
@rengaraj-89Rrct โ€ข Oct 22, 2024

Sir / madam,
My question is

Some work is done by two people in 24 minutes. One of them can do this work alone in 40 minutes. How much time does the second person take to do the same work ?
a. 48 Min
b. 16 Min
c. 72 Min
d. 60 Min

Advance Thanks,
R.Rengaraj
{SCE 31/2008/Pg 4 of 85}
{On this forum my 8th Question.}

Replies

Welcome, guest

Join CrazyEngineers to reply, ask questions, and participate in conversations.

CrazyEngineers powered by Jatra Community Platform

  • tech_vaibhav_ee

    @tech-vaibhav-ee-65Xzvs Nov 21, 2009

    let us give a value to the total amount of work =x
    person a: 40 mins. --> x
    24 mins. --> 24x/40

    person b: y mins. -->x
    24mins -->24x/y

    when working together , they complete the whole work in 24 mins.

    therefore,
    24x/40 +24x/y = x
    y=60 mins..
    hence , person b completes the same work in 60 minutes.