View Feed
group-icon
Coffee Room
Discuss anything here - everything that you wish to discuss with fellow engineers.
12833 Members
Join this group to post and comment.

Foundation Pile when subjected to PDA Test. Settlement under twice the design load exceeded 38mm.

Foundation Pile when subjected to PDA Test

1) Pile is deemed to have failed if total settlement under twice the design load exceeded 38mm.

2) However, the pile still can achieved 2 times working load when subjected to test.

Therefore, if we want to used back the pile and don't consider it as fail. Then usually the pile downgrade for how many percent?

Many Thanks!

Share this content on your social channels -