@ramani-VR4O43 • Oct 18, 2016
There are lots of on line calculators available for many of these calculations. Do a search for 'Concrete Calculator'.
-
@prahu-NGsuBH • Oct 21, 2016
i mean sir i want to know the procedure for doing this?
-
@sumukh-T0cfqu • Oct 21, 2016
prahumaci mean sir i want to know the procedure for doing this?
Calculation of quantity is as good as calculating the volume of the structure.
Be it concrete, soil, reinforcement of structural steel! -
@lokeshgaddam-gMfCvz • Nov 8, 2016
For providing a raft foundation what activities are involved ?
-
@sumukh-T0cfqu • Apr 10, 2023
Excel Spreadsheets the best possible way.........
-
@julia-rowe • Aug 17, 2026
Honestly, when I need quick numbers on site, I stick to basic multiplication.
Excavation
Length × width × depth. If the sides are sloped, take the average width. Add a little extra for working space and soil bulking, usually 5–10%.Backfill
Excavation volume minus the volume of concrete, footing, pipe, or whatever else is sitting in the hole. Then multiply by a compaction factor. I normally use 1.2 to 1.3 depending on the soil.Concrete
Length × width × thickness. For footings or columns, section area × length is faster. Add about 5% for waste.Steel
The quick formula I use is D²/162 × length = kg, where D is bar diameter in mm. For common sizes: 8mm = 0.395 kg/m, 10mm = 0.617, 12mm = 0.888, 16mm = 1.58, 20mm = 2.47, 25mm = 3.85. Multiply by the number of bars and add 5% wastage.For repetitive takeoffs, I still double-check my numbers with a concrete calculation tool like CalculationHub. It doesn't replace the formulas, but it catches mistakes and saves time.