Order of pouring concrete at site

gopaldeshpande

gopaldeshpande

@gopaldeshpande-gfHC7U Oct 26, 2024
why is concrete poured in beams first and then in slab?

Replies

Welcome, guest

Join CrazyEngineers to reply, ask questions, and participate in conversations.

CrazyEngineers powered by Jatra Community Platform

  • Jeffrey Arulraj

    Jeffrey Arulraj

    @jeffrey-xA7lUP May 28, 2013

    Can you elaborate this

    I think based on the order of construction this is done

    You can't build a transverse structure with out providing adequate support to withstand the load and traverse it to the ground
  • gopaldeshpande

    gopaldeshpande

    @gopaldeshpande-gfHC7U May 28, 2013

    Conqueror
    Can you elaborate this

    I think based on the order of construction this is done

    You can't build a transverse structure with out providing adequate support to withstand the load and traverse it to the ground


    can you explain this in detail?
  • Anil Jain

    Anil Jain

    @CrazyBoy May 28, 2013

    They are laid in the order...In normal residential structures, the only feasible arrangement for the concrete slabs is either on supporting columns, walls or beams.

    So, there is *no* way we can think of laying a slab before the beam, right?

    Am I missing something hidden in question?